1 |
30-10-24-25 |
Construction of Gymkhana Building at Trimohini Pratap Chandra HS School in vill-Trimohini GP-Dhalpara in P.S.Hili |
|
Nihar Ghosh |
04/12/2024 |
₹1,287,255.00 |
10/03/2025 |
276/ZP |
Not started |
60
|
5th SFC (24-25) |
|
2 |
|
Installation of Solar Street Light at front side of Kasiya Danga Durga Mandir and other 5 side, GP_Jalghar in P.S. Balurghat-90884481 |
|
Nihar Ghosh |
04/12/2024 |
₹281,913.00 |
10/03/2025 |
275/ZP |
Not started |
60
|
15th FC TIED (23-24) |
|
3 |
30-08-24-25 |
Installation of Solar Street Light at Babtal GP_Rampara Chenchra in P.S. Tapan-90889821 |
|
Nihar Ghosh |
04/12/2024 |
₹469,855.00 |
10/03/2025 |
274/ZP |
Not started |
60
|
15th FC TIED (23-24) |
|
4 |
30-07-24-25 |
Installation of Mini Mast with LED Solar Light at Hazratpur GP Office, GP-Hazratpur in P.S. Tapan-68388933 |
|
Nihar Ghosh |
04/12/2024 |
₹516,841.00 |
10/03/2025 |
273/ZP |
Not started |
60
|
15th FC TIED (23-24) |
|
5 |
30-06-24-25 |
Installation of Solar Street Light front side of Pagliganj Bridge to Khaspur Hospital, GP-Boaldar in P.S. Balurghat-70384149 |
|
Nihar Ghosh |
04/12/2024 |
₹563,826.00 |
10/03/2025 |
272/ZP |
Not started |
60
|
15th FC TIED (23-24) |
|
6 |
30-03-24-25 |
Construction of Solid Waste management Unit and other related work at Chaloon GP(light), Chaloon in P.S. Gangarampur-70746066 |
|
Nihar Ghosh |
04/12/2024 |
₹986,696.00 |
10/03/2024 |
271/ZP |
Not started |
60
|
15th FC UN-TIED (23-24) |
|
7 |
30-02-24-25 |
Installation of Mini Mast with LED Solar Light at Kardha Bus Stand, GP- Ramchandrapur in P.S. Tapan-68389209 |
|
Nihar Ghosh |
04/12/2024 |
₹516,841.00 |
10/03/2024 |
270/ZP |
Not started |
60
|
15th FC UN-TIED (23-24) |
|
8 |
30-01-24-25 |
Installation of Solar Street Light front side of Mohana Petrol Pump to Madhyaramkrishnapur, GP- Ramkrishnapur in P.S. Kumarganj-70377172 |
|
Nihar Ghosh |
12/04/2024 |
₹986,696.00 |
10/03/2025 |
269/ZP |
Not started |
60
|
15th FC UN-TIED (23-24) |
|
9 |
29-14-24-25 |
Construction of Boundary wall with School gate at Sukdevpur High School in Sukdevpur GP in P.S. Gangarampur-91068532 |
|
PABAN BASAK |
04/12/2024 |
₹861,413.00 |
10/03/2025 |
270/ZP |
Not started |
60
|
15th FC UN-TIED (24-25) |
|
10 |
29-13-24-25 |
Construction of CC Road from the end point of old PCC road towards Khorchuna village Tinmatha more under Karanji GP in P.S. Kushmandi.-90131165 |
|
Kalyan Bose |
04/12/2024 |
₹582,692.00 |
10/03/2025 |
269/ZP |
Not started |
60
|
15th FC UN-TIED (24-25) |
|
11 |
29-11-24-25 |
Construction of Vented Causeway at Taltala, Nachuapara road under Ganguria GP in P.S. Banshihari. |
|
Kalyan Bose |
04/12/2024 |
₹6,294,190.00 |
10/03/2025 |
268/ZP |
Not started |
120
|
5th SFC (24-25) |
|
12 |
29-10-24-25 |
Construction of CC Road from Malpara Faijul Mondal House to Uttarpara Tanbeer Al Aman House in vill-Tetrail under Uday GP in P.S. Gangarampur |
|
PABAN BASAK |
04/12/2024 |
₹1,456,731.00 |
10/03/2025 |
267/ZP |
Not started |
90
|
5th SFC (24-25) |
|
13 |
29-09-24-25 |
Construction of Open Stage at Thangapara High School in Belbari-II GP under Gangarampur. |
|
PABAN BASAK |
04/12/2024 |
₹631,250.00 |
10/03/2025 |
266/ZP |
Not started |
60
|
5th SFC (24-25) |
|
14 |
29-08-24-25 |
Construction of Crematorium at Khanpur Sashan in Bramhangram Sansad under Pundari GP in P.S. Harirampur |
|
Kalyan Bose |
04/12/2024 |
₹485,351.00 |
10/03/2025 |
265/ZP |
Not started |
60
|
BEUP |
|
15 |
29-07-24-25 |
Instalation & Supply of Solar Based over Head Running Drinking Water in Vill- Dangabiral under Gopalbati GP in P.S. Balurghat |
|
PABAN BASAK |
04/12/2024 |
₹990,193.00 |
10/03/2025 |
264/ZP |
Not started |
|
5th SFC (24-25) |
|
16 |
29-06-24-25 |
Construction of RCC Covered Drain from Bhai Bhai more to Badanikum in vill- Badanikum under Belbari-IGP in P.S. Gangarampur-47404773 |
|
PABAN BASAK |
04/12/2024 |
₹971,155.00 |
10/03/2025 |
263/ZP |
Not started |
90
|
15th FC TIED (21-22) |
|
17 |
29-05-24-25 |
Construction of Crematorium 1. At Choto Sihoil Sashan under Ellahabad GP(Mouza-Bhingaldaha, JL No- 223 Plot no- 371/802) 2. At Biswanathpur Sasan under Ganguria GP(Mouza-Bil Barail, JL No- 279 Plot No- 83,84) 3. At Chini Chatang Sasan under Mahabri GP(Mouza-Baje-Rupahata JL No-185 Plot No- 264) in P.S. Banshihari. |
|
Kalyan Bose |
04/12/2024 |
₹1,456,052.00 |
10/03/2025 |
262/ZP |
Not started |
90
|
BEUP |
|
18 |
29-04-24-25 |
Construction of SWM unit with CC road from NH-512 towards CPU in vill-Gochihar, GP-Damdama in P.S. Gangarampur-70737493 |
|
PABAN BASAK |
04/12/2024 |
₹990,196.00 |
10/03/2025 |
261/ZP |
Not started |
90
|
15th FC UN-TIED (23-24) |
|
19 |
29-02-24-25 |
Construction of CC Road from Kanjhara more to Kanjhara Masjid(except old CC road) under Elahabad GP in P.S. Banshihari-69349585 |
|
Kalyan Bose |
04/12/2024 |
₹1,165,436.00 |
10/03/2025 |
260/ZP |
Not started |
90
|
15th FC UN-TIED (23-24) |
|
20 |
28-12-24-25 |
Construction of Crematorium 1. At Sukandighi Sasan under Sayedpur GP(JL No-89 Plot No- 1280, Mouza-Bartaki gram) 2. At Nakahar Sasan under Gokarna GP(Mouza-Lahuchar, JL No- 193) 3. At Naoga under Shirshi GP(Mouza-Naoga JL No- 40 Plot No- 308) 4. At Jhalkuriya Sasan under Bairhatta GP(Mouza-Mahendra JL No- 08) in Harirampur Block. |
|
Kalyan Bose |
27/11/2024 |
₹1,941,402.00 |
04/02/2025 |
BEUP |
Not started |
90
|
BEUP |
|
21 |
28-11-24-25 |
Construction of CC Road from Sankopara towards Banshkuri, Udaypur GP in P.S-90128545 |
|
Kalyan Bose |
27/11/2024 |
₹1,187,617.00 |
04/02/2025 |
126/ZP |
Not started |
90
|
15th FC UN-TIED (24-25) |
|
22 |
28-10-24-25 |
Construction of Covered Drain from Mastafa Sarkar house towards al-amin mission(east side) end point of Nakair, Uday, Gangarampur-60870786 |
|
PABAN BASAK |
27/11/2024 |
₹2,912,620.00 |
04/02/2025 |
125/ZP |
Not started |
90
|
15th FC TIED (20-21) |
|
23 |
28-09-24-25 |
Construction of Toilet block at Dhapatala, Mahabullapur under Maligaon GP in P.S. Kushmandi-89430738 |
|
Kalyan Bose |
27/11/2024 |
₹971,123.00 |
04/02/2025 |
124/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
24 |
28-06-24-25 |
Construction of Community Toilet at front side of Baniyapara Market under Bhatpara GP in P.S. Balurghat-9426890 |
|
SMRITI CHANDRA KARMAKAR |
27/11/2024 |
₹988,249.00 |
04/02/2025 |
123/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
25 |
28-04-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Jarjish House, GP-Brajaballavpur in P.S. Banshihari-97992441 |
|
Nihar Ghosh |
27/11/2024 |
₹771,397.00 |
04/02/2024 |
122/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
26 |
28-03-24-25 |
Construction of Toilet Block at Daulatpur Police Camp, Mahammadpur under Ganguria GP In P.S. Banshihari-89429589 |
|
Kalyan Bose |
27/11/2024 |
₹971,123.00 |
04/02/2025 |
121/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
27 |
28-02-2024 |
Repair and maintenance of CC Road from Nurpur More towards Doutpur village, GP-Ellahabad in PS Banshihari. |
|
Kalyan Bose |
27/11/2024 |
₹1,188,093.00 |
27/11/2024 |
|
Not started |
90
|
5th SFC (24-25) |
|
28 |
28-01-24-25 |
Construction of RCC covered Drain from H/O Mokbul Mondal towards H/O latib Mandal House in vill Khottapara under Batun GP in P.S. Kumarganj-58357242 |
|
PABAN BASAK |
27/11/2024 |
₹1,485,294.00 |
04/02/2025 |
119/ZP |
Not started |
90
|
15th FC TIED (22-23) |
|
29 |
27-14-24-25 |
Construction of RCC covered Drain from H/O Tajruddin Mondal towards H/O Ajiz Mondal House in vill-Pirozpur under Mohona GP in P.S. Kumarganj-89431656 |
|
PABAN BASAK |
27/11/2024 |
₹925,157.00 |
11/02/2025 |
157/ZP |
Not started |
60
|
15th FC TIED (24-25) |
|
30 |
27-13-24-25 |
Construction of Cement Concrete Road from Pucca Road towards Ulipur village under Jakirpur GP In P.S. Kumarganj-70757048 |
|
PABAN BASAK |
27/11/2024 |
₹990,195.00 |
11/02/2025 |
156/ZP |
Not started |
60
|
15th FC UN-TIED (23-24) |
|
31 |
27-09-24-25 |
Construction of SBOHRD at Benail-Kashipara, pundari GP In P.S. Harirampur-47391294 |
|
Kalyan Bose |
27/11/2024 |
₹967,217.00 |
11/02/2025 |
155/ZP |
Not started |
60
|
15th FC TIED (21-22) |
|
32 |
27-08-24-25 |
Construction of CC Road from bara RIDF road towards Naradas Primari School with Nara Devsharma house link road(except old CC portion) under Shirshi GP in P.S. Harirampur-47439484 |
|
Kalyan Bose |
27/11/2024 |
₹1,553,840.00 |
11/02/2025 |
54/ZP |
Not started |
60
|
15th FC UN-TIED (21-22) |
|
33 |
27-07-24-25 |
Construction of Covered Drain from Balipukur Juma Masjit towards Raja Islam House, Balipukur, Mahabri in P.S. Banshihari- |
|
Kalyan Bose |
11/02/2025 |
₹1,456,296.00 |
11/02/2025 |
153/ZP |
Not started |
60
|
15th FC TIED(supplementary) (23-24 |
|
34 |
|
Installation of Solar Powred LDTW for Minor Irrigation at the land of Sukumar Ghosh, Mouja-Narayanpur, GP-Belbari in P.S. Gangarampur-89449580 |
|
Nihar Ghosh |
27/11/2024 |
₹873,977.00 |
11/02/2025 |
151/ZP |
Not started |
60
|
15th FC TIED (24-25) |
|
35 |
27-04-2025 |
Installation of Solar Powred Water ATM in near Kakna Durga Mandir, Autina in P.S. Tapan-89975471 |
|
Kalyan Bose |
27/11/2024 |
₹523,474.00 |
11/02/2025 |
150/ZP |
Not started |
60
|
15th FC TIED (24-25) |
|
36 |
27-03-24-25 |
Installation of Solar Powred Water ATM in near Anatar Masjit, Ajmatpur, Tapan-89975110 |
|
Kalyan Bose |
27/11/2024 |
₹523,266.00 |
11/02/2025 |
149/ZP |
Not started |
60
|
15th FC TIED (24-25) |
|
37 |
27-1-24-25 |
Construction of CC Road from Shibpur PMGSY towards Rail Line in P.S. Balurghat. |
|
PABAN BASAK |
27/11/2024 |
₹599,984.00 |
11/02/2025 |
148/ZP |
Not started |
60
|
5th SFC (24-25) |
|
38 |
26-01-24-25 |
Supply & Installation of Water Purifier cum Chiller Machine in BIsrail High School, Thangapara High School, Sukdevpur High School, Jahangirpur High School, Bajitpur High School, Malipara High School, Bikoir Sabuj Sathi Club, Patiram Jamini Majumdar College, Basuria Abeskuri High School, Niranjan Smriti VIdyapith and Ratanpur more public Toilet.-89966314 |
|
PABAN BASAK |
12/11/2024 |
₹1,930,884.00 |
04/02/2025 |
118/ZP |
Not started |
90
|
15th FC (24-25) |
|
39 |
24-01-24-25 |
Installation of Faecal Sludge and Septage Treatment Plant of 20 KLD Capacity Based on Enhanced Digestion and Multistage Bioreactor (EDMSB) Technology for Kushmandi Block in the District of Dakshin Dinajpur. |
|
PABAN BASAK |
03/10/2024 |
₹21,122,750.00 |
29/11/2024 |
1365/ZP |
Not started |
270
|
SBM-G |
|
40 |
22-07-24-25 |
Construction of Cover Drain from Ancher Ali House towards Ismail Miah land in GP Sukdevpur under Gangarampur PS |
|
PABAN BASAK |
01/10/2024 |
₹1,068,269.00 |
01/01/1970 |
1557/ZP |
Not started |
90
|
5th SFC (24-25) |
|
41 |
22-05-24-25 |
Construction of Covered Drain from Kardaha Amlan Ghosh House towards Bibadi Club under Ramchandrapur GPin P.S. Tapan-89391052 |
|
PABAN BASAK |
01/10/2024 |
₹1,456,298.00 |
31/12/2024 |
1556/ZP |
Not started |
90
|
15th FC (2024-24) |
|
42 |
22-4-24-25 |
Construction of Covered Drain from Dangarhat Fish Bazar towards House of Goffar Sarkar under Ramkrishnapur GP in P.S. Kumarganj-89387805 |
|
PABAN BASAK |
01/10/2024 |
₹1,359,615.00 |
31/12/2024 |
1555/ZP |
Not started |
90
|
15th FC (2024-24) |
|
43 |
20-03-24-25 |
Construction of CC Road from Hasen Ali House to Anis Fakir House in village Gokulpur Ashokegram GP in P.S. Gangarampur-90126805 |
|
PABAN BASAK |
01/10/2024 |
₹1,188,235.00 |
31/12/2024 |
1554/ZP |
Not started |
90
|
15th FC (2024-24) |
|
44 |
22-02-24-25 |
Construction of CC Road from Ghugudanga Primary School towards Bisoridanga more Ganguria GP in P.S. Banshihari- |
|
Kalyan Bose |
01/10/2024 |
₹1,484,670.00 |
11/03/2025 |
297/ZP |
Not started |
90
|
5th SFC (24-25) |
|
45 |
22-01-24-25 |
Repairing of Box Bridge at Sulpanipur under Gofanagar GP in P.S. Tapan. |
|
Kalyan Bose |
01/10/2024 |
₹1,241,152.00 |
11/03/2025 |
296/ZP |
Not started |
90
|
5th SFC (24-25) |
|
46 |
21-01-24-25 |
Supplying of Garbage Loader (Three wheeler battery operated E-rickshaw/E-cart with up to 800 kg capacity & hydraulic trolley) i) Exide/Amara-Raja/Livguard battery of 100 Ah (5pcs) with 12 month warranty ii) Charger 15 AMP SMPS iii) Heavy Iron Body, Telescopic front Shocker with leaf spring and Galvanized (GI)sheet, iv) Rear Shocker v) 1.000 KW 55 Amp Motor vi) 60 volt 1000 watt |
|
Nihar Ghosh |
01/10/2024 |
₹4,455,000.00 |
03/12/2024 |
1406/ZP |
Not started |
15
|
SBM-G |
|
47 |
20-10-24-25 |
Construction of cover drain from Mithun Das House towards Shibtali More under Dhalpara GP in PS – Hili |
|
PABAN BASAK |
25/09/2024 |
₹891,175.00 |
03/12/2024 |
1419/ZP |
Not started |
90
|
5th SFC (24-25) |
|
48 |
20-09-24-25 |
Construction of CC Road from towards Biplab Das House towards Binoy Shil House under Raamkrishnapur GP in PS - Kumarganj |
|
PABAN BASAK |
25/09/2024 |
₹582,692.00 |
03/12/2024 |
1418/ZP |
Not started |
90
|
5th SFC (24-25) |
|
49 |
20-08-24-25 |
Construction of cc road from Sami Baskey House to Bikul Tudu House, Ajmatpur, in PS – Tapan – 90129246 |
|
Kalyan Bose |
25/09/2024 |
₹971,153.00 |
03/12/2024 |
1417/ZP |
Not started |
90
|
15th FC (24-25) |
|
50 |
20-07-24-25 |
Construction of Cover Drain From Nandan Sarkar Pond towards Baro Sako Bridge Sirsi in PS – Harirampur- 89981930 |
|
Kalyan Bose |
25/09/2024 |
₹970,872.00 |
03/12/2024 |
1416/ZP |
Not started |
90
|
15th FC (24-25) |
|
51 |
20-06-24-25 |
Construction of CC Road from Jodguri To Kabarstan under Bagichapur GP in PS – Harirampur - |
|
Kalyan Bose |
25/09/2024 |
₹679,806.00 |
03/12/2024 |
1415/ZP |
Not started |
90
|
5th SFC (24-25) |
|
52 |
20-05-24-25 |
Construction of CC Road from Dolgram Mina Road towards Fagu more via Keramuddin Mia House under Bagichapur GP in PS – Harirampur- 90126575 |
|
Kalyan Bose |
25/09/2024 |
₹874,038.00 |
03/12/2024 |
1441/ZP |
Not started |
90
|
15th FC (24-25) |
|
53 |
20-04-24-25 |
Construction of CC Road from Monsur Shekh hose towards Idgha.(Except old CC road) under Sirsi GP in PS - Harirampur- 90328422 |
|
Kalyan Bose |
25/09/2024 |
₹971,140.00 |
03/12/2024 |
1414/ZP |
Not started |
90
|
15th FC (24-25) |
|
54 |
20-02-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Najrul Miah Mouja-Barampur, GP-Hazratpur in P.S. Tapan-89962451 |
|
Nihar Ghosh |
25/09/2024 |
₹876,896.00 |
03/12/2024 |
1413/ZP |
Not started |
60
|
15th FC (24-25) |
|
55 |
20-01-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Selina Sarkar Mouja-Tarait, GP-Ramchandrapur in P.S. Tapan-89962025 |
|
Nihar Ghosh |
25/09/2024 |
₹876,896.00 |
03/12/2024 |
1412/ZP |
Not started |
60
|
15th FC (24-25) |
|
56 |
19-11-24-25 |
Civil and Electrical installation works for UPS system & DG set platform at newly constructed Public Health Unit (Tapan BPHU) under XV FC-HG FY 2021-22. |
|
Nihar Ghosh |
25/09/2024 |
₹220,307.00 |
03/12/2024 |
1411/ZP |
Not started |
60
|
XV FC-HG FY 2021-22 |
|
57 |
19-07-24-25 |
Supply & Installation of Solar Pump with Drinking Water near Prokash Ch Sarkar house in GP Nandanpur in PS - Gangarampur |
|
PABAN BASAK |
25/09/2024 |
₹539,962.00 |
03/12/2024 |
1410/ZP |
Not started |
90
|
5th SFC (24-25) |
|
58 |
19-02-24-25 |
Construction of CC Road from Borakuri footbal math towards Balihar BT road under Ramchandra GP in PS – Tapan – 90903082 |
|
Kalyan Bose |
25/09/2024 |
₹971,154.00 |
03/12/2024 |
1408/ZP |
Not started |
90
|
15th FC (24-25) |
|
59 |
19-01-24-25 |
Construction of CC Road from Sadekul Miah House towards Kojagori Mandir under Dwipkhanda GP in PS - Tapan - 90323694 |
|
Nihar Ghosh |
25/09/2024 |
₹0.00 |
03/12/2024 |
1407/ZP |
Not started |
90
|
15th FC (24-25) |
|
60 |
16-12-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Jopen Sarkar GP – Udaypur, in P.S. Kushmandi -97993194 |
|
Nihar Ghosh |
05/09/2024 |
₹771,397.00 |
02/12/2024 |
1404/ZP |
Not started |
60
|
5th SFC |
|
61 |
16-06-24-25 |
Installation of Solar Mini Mast Light front side of Youbo nantha Sanstha Belbari, GP-Belbari-I in P.S. Gangarampur-90878165 |
|
Nihar Ghosh |
05/09/2024 |
₹434,984.00 |
02/12/2024 |
1403/ZP |
Not started |
60
|
15th FC(24-25) |
|
62 |
16-05-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Mahabur Islam Mouja-Kutubpur GP-Pundari in P.S. Harirampur-89438901 |
|
Nihar Ghosh |
05/09/2024 |
₹865,131.00 |
02/12/2024 |
1402/ZP |
Not started |
60
|
15th FC (24-25) |
|
63 |
16-04-24-25 |
Construction of CC Road from Doan Kali Mandir towards the house of Sunil Mali at Shiala under Chinsgispur GP in P.S. Balurghat |
|
SMRITI CHANDRA KARMAKAR |
05/09/2024 |
₹582,692.00 |
02/12/2024 |
1401/ZP |
Not started |
60
|
5th SFC (24-25) |
|
64 |
16-03-24-25 |
Construction of Covered Drain from Debdulal House towards Kadamtali FP School under Patiram GP in P.S. Balurghat-89385313 |
|
PABAN BASAK |
05/09/2024 |
₹971,153.00 |
02/12/2024 |
1400/ZP |
Not started |
60
|
15th FC (24-25) |
|
65 |
16-01-24-25 |
Installation of Solar Powred Water ATM infront of Sarala Hatkhola GP-Beroil under Kushmandi PS. |
|
Kalyan Bose |
05/09/2024 |
₹544,599.00 |
02/12/2024 |
1399/ZP |
Not started |
60
|
15th FC (24-25) |
|
66 |
15-10-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Anjuyara Bibi(Begam) Mouja- Boromaha GP-Bairahatta in P.S. Harirampur-89438484 |
|
Nihar Ghosh |
04/09/2024 |
₹865,131.00 |
29/11/2024 |
1370/ZP |
Not started |
60
|
15th FC (24-25) |
|
67 |
15-07-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Jiten Singha Mouja-Bilborail GP-Ganguria in P.S. Banshihari.-89963892 |
|
Nihar Ghosh |
01/01/1970 |
₹771,397.00 |
29/11/2024 |
1369/ZP |
Not started |
60
|
15th FC (24-25) |
|
68 |
15-06-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Rasidur Miah Mouja-Biswaspukur GP-Ashokgram in P.S. Gangarampur-89440383 |
|
Nihar Ghosh |
04/09/2024 |
₹865,787.00 |
29/11/2024 |
1368/ZP |
Not started |
60
|
15th FC (24-25) |
|
69 |
15-05-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Pradip Basak, Mouza-Gokulpur GP-Ashokgram in P.S. Gangarampur-89439257 |
|
Nihar Ghosh |
04/09/2024 |
₹865,787.00 |
29/11/2024 |
1367/ZP |
Not started |
60
|
15th FC (24-25) |
|
70 |
15-01-24-25 |
Installation of Solar Powered LDTW for Minor Irrigation at the land of Jasimiddin Miah in GP-Ashokgram in P.S. Gangarampur-97973856 |
|
Nihar Ghosh |
04/09/2024 |
₹865,787.00 |
28/11/2024 |
1366/ZP |
Not started |
60
|
5th SFC (24-25) |
|
71 |
14-01-24-25 |
Construction of Box Bridge (4 nos x 6.0 m x 6.0 m) at Rupahata under Banshihari Block, Dist- Dakshin Dinajpur |
|
Kalyan Bose |
28/08/2024 |
₹12,475,474.00 |
10/12/2024 |
1465/ZP |
Not started |
365
|
5th SFC (24-25) |
|
72 |
13-06-24-25 |
Installation and Supply of Solar Based Street Light at Udaypur and maligaon GP in P.S. Kushmandi-977876614 |
|
Kalyan Bose |
28/08/2024 |
₹1,268,609.00 |
18/12/2024 |
1523/ZP |
Not started |
60
|
5th SFC (24-25) |
|
73 |
13-05-24-25 |
Boring Lowering & Installation for existing Solar Powered Pump set on different places(land of Marium Hembrom, Budiya Biha, Anchar Ali & Shed Ali Sarkar) under Tapan Block-107240218 |
|
Kalyan Bose |
28/08/2024 |
₹1,190,997.00 |
18/12/2024 |
1522/ZP |
Not started |
60
|
15th FC-TIED (22-23)-Supplementary |
|
74 |
13-03-24-25 |
Construction of Covered Drain from Mantu Sarkar House towards East Side River at Darajpur under Jakirpur GP in P.S. Kumarganj. |
|
PABAN BASAK |
28/08/2024 |
₹1,165,384.00 |
18/12/2024 |
1521/ZP |
Not started |
90
|
5th SFC (24-25) |
|
75 |
13-02-24-25 |
Construction of Covered Drain from Ranjit Ghosh House(Maderganj) towards Sibesh Ghosh Shop with Soak Pit under Batun GP in P.S. Kumarganj-89382504 |
|
PABAN BASAK |
28/08/2024 |
₹1,456,731.00 |
18/12/2024 |
1520/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
76 |
13-01-24-25 |
Construction of Covered Drain from Naresh Mali House towards Sunodh Das House under HiliGP in P.S. Hili. |
|
PABAN BASAK |
28/08/2024 |
₹1,553,845.00 |
18/12/2024 |
5th SFC (24-25) |
Not started |
90
|
5th SFC (24-25) |
|
77 |
12-12-24-25 |
Installation & Supply of Solar High Mast Light at Chandipur High School Math, GP-Gokarna in P.S. Harirampur-97792427 |
|
Nihar Ghosh |
28/08/2024 |
₹434,984.00 |
18/12/2024 |
1518/ZP |
Not started |
60
|
5th SFC (24-25) |
|
78 |
12-11-24-25 |
Installation & Supply of Solar High Mast Light at Belbari Goyalpara, GP-Belbari-I in P.S. Gangarampur -97824452 |
|
Nihar Ghosh |
28/08/2024 |
₹434,984.00 |
18/12/2024 |
1517/ZP |
Not started |
60
|
5th SFC (24-25) |
|
79 |
12-10-24-25 |
Installation & Supply of Solar Light at Bhakla Sansad-5 pc and Kalikamora GP-6 pc, Berul GP-1 pc in P.S. Kushmandi-97625612 |
|
Nihar Ghosh |
28/08/2024 |
₹563,826.00 |
18/12/2024 |
1516/ZP |
Not started |
60
|
5th SFC (24-25) |
|
80 |
12-09-24-25 |
Installation & Supply of Solar Light at Patiram College- 3 pc, Najirpur GP area-3 pc & Danga GP- 6, in P.S. Balurghat-97653700 |
|
Nihar Ghosh |
28/08/2024 |
₹563,826.00 |
18/12/2024 |
1515/ZP |
Not started |
60
|
|
|
81 |
12-08-24-25 |
Construction of Covered Drain from Molladighi Bus Stand towards Rabi Sardar House in the end under Samjia GP in P.S. Kumarganj. |
|
PABAN BASAK |
28/08/2024 |
₹874,038.00 |
18/12/2024 |
1514/ZP |
Not started |
90
|
5th SFC (24-25) |
|
82 |
12-07-24-25 |
Construction of Covered Drain from Sitahar Masjit towards the House of Mahsin Miah House under Bhour GP in P.S. Kumarganj-89388879 |
|
PABAN BASAK |
28/08/2024 |
₹971,154.00 |
18/12/2024 |
1513/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
83 |
12-06-24-25 |
Construction of Covered Drain from Dakshin Panjul More towards Budhu Mahato Doba Land under Panjul GP in P.S. Hili-89385991 |
|
PABAN BASAK |
28/08/2024 |
₹971,154.00 |
18/12/2024 |
1512/ZP |
Not started |
90
|
15th FC TIED (24-25) |
|
84 |
12-05-24-25 |
Construction of CC Road from land of Bikash Pramanik towards Amal Mali House under Danga GP in P.S. Balurghat-90130358 |
|
PABAN BASAK |
28/08/2024 |
₹990,196.00 |
18/12/2024 |
1511/ZP |
Not started |
90
|
15th FC UN-TIED (24-25) |
|
85 |
12-04-24-25 |
Construction of CC Road from Foodkalai towards Harkata under Bhour GP in P.S. Kumarganj-90321691 |
|
PABAN BASAK |
28/08/2024 |
₹971,154.00 |
18/12/2024 |
1510/ZP |
Not started |
90
|
15th FC UN-TIED (24-25) |
|
86 |
12-03-24-25 |
Construction of CC Road from Harin Kuri Pacca Road towards West Side Vhaluk Kuri under Bhour GP in P.S. Kumarganj. |
|
PABAN BASAK |
28/08/2024 |
₹582,692.00 |
18/12/2024 |
1509/ZP |
Not started |
90
|
5th SFC (24-25) |
|
87 |
12-02-24-25 |
Construction of CC Road from Binu Roy House east side Hasan Mandal House under Jakirpur GP in P.S. Kumarganj-90122505 |
|
PABAN BASAK |
28/08/2024 |
₹971,154.00 |
18/12/2024 |
1508/ZP |
Not started |
90
|
15th FC UN-TIED (24-25) |
|
88 |
11-01-24-25 |
Yearly repairing and maintenance of Electrical Works under ZP Premises and another Building-40102 |
|
Nihar Ghosh |
26/07/2024 |
₹150,000.00 |
04/09/2024 |
1050/ZP |
Not started |
365
|
5th SFC |
|
89 |
10-08-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Naogoan High School, RCA magurpur High School, Kardaha High School, Ramchandrapur High School, Vior Jalaliya Bakhar , Bhadrail, Tilon , Tapan Nathaliyan Murmu Memorial Collage , Daralhat, Balapur High School ,Tapan Girls, Tapan ,Baniyal apan Block under DDZP-44812682 |
|
Kalyan Bose |
24/07/2024 |
₹346,568.00 |
29/10/2024 |
1259/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
90 |
10-07-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Deor Sanaulla, Sitahar Mulgram , Gourangopur, Kumarganj Safanagar , Ellendari, Kulohari , Balupara Girls, Gopalganj RN , Kumarganj College, Dangar Hat High School , Patiram Pather Sathi (Patiram GP, Balurghat Block),Patiram G.P. Office (Patiram GP, Balurghat Block),Anghina Borot High School, Sundarpur Girls High School ,Tulot High School, Manjurichak Raikhan High School,Saidpur BMA -44812723 |
|
PABAN BASAK |
24/07/2024 |
₹495,098.00 |
29/10/2024 |
1258/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
91 |
10-05-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Hili High School, Hili Girls High School,Teor Sarbeswar Balika Bidhyalaya,Teor Govt. Sponsored Balika Bidyalaya of Hili Block under DDZP-44812741 |
|
PABAN BASAK |
24/07/2024 |
₹99,019.00 |
29/10/2024 |
1257/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
92 |
10-05-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Sairapur High School, Fulbari High School, Belbari High School, Niranjan Smriti High School, Raghobpur High School, Jaghagirpur High School, Ashokgram High School, Nehemba High School, Gangarampur Girls High School, Sukdebpur High School, Holy Crose Girls High School ,Gangarampur Collage ,Narai Moulana Azad Academy ,Chaloon High School ,G.M Girls Academy ,Banihari High School ,Gangarampur-44812847 |
|
PABAN BASAK |
24/07/2024 |
₹495,098.00 |
29/10/2024 |
1256/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
93 |
10-04-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Daulatpur High School, Ganguria High School, Bagduar MSK, Haripur Bes an Nur Model Girls Mission,Belpukur High Madrasha ,Pathar ghata High School of Banshihari Block under DDZP-44812878 |
|
Kalyan Bose |
24/07/2024 |
₹148,530.00 |
29/10/2024 |
1255/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
94 |
10-03-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at ASDM High School, Khayerbari High School, Lohachar High School ,Danab Gram I.C. Hich School of Harirampur Block under DDZP-44812903 |
|
Kalyan Bose |
24/07/2024 |
₹99,019.00 |
29/10/2024 |
1254/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
95 |
10-02-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Katabri High School, Lohaganj High School, Aminpur High School, Nahit High School, Parpmeswarpur High School, Khagail Tankanath High School, Mahipal High School, Dhakdhol High School,Chandipur High School (Gokarna gp, Harirampur block), Belbari GP Office(Belbari-1, Gangarampur Block), Nadan High Madrasha (Dwipkhanda GP, Tapan Block) ,Mangalpur Adhi Basi High School ,Chousa -44812954 |
|
Kalyan Bose |
24/07/2024 |
₹396,078.00 |
29/10/2024 |
1253/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
96 |
10-01-24-25 |
Supplying & Installation of Sanitary napkin vending Machine & Incinerator at Chingispur High School, Sobra High School, Kurmail Sonapara SC High School, Barkail High School, Chakram BL High School, Kuchila High School, Khidirpur High School, Ajadhya Kalibari High School, Patiram Jamini Majumder Memorial Collage , N.C. Girls High School , Khadimpur Girls High School ,Balurghat Girlool |
|
PABAN BASAK |
24/07/2024 |
₹396,078.00 |
29/10/2024 |
1252/ZP |
Not started |
45
|
15th FC TIED (20-21) |
|
97 |
09-06-24-25 |
Installation of Solar High Mast Light in front of Kokil more MR Delar’s Shop under Pundari GP in P.S. Harirampur |
|
Nihar Ghosh |
23/07/2024 |
₹434,984.00 |
29/10/2024 |
1251/ZP |
Not started |
90
|
BEUP 42 |
|
98 |
09-05-24-25 |
Installation of Solar High Mast Light at Bhitar Mushan Hatkhola under Brajaballavpur GP in P.S. Banshihari |
|
Nihar Ghosh |
23/07/2024 |
₹434,984.00 |
29/10/2024 |
1250/ZP |
Not started |
90
|
BEUP 42 |
|
99 |
09-02-24-25 |
Installation of Solar High Mast Light at Kalyanni More under Mahabari GP in P.S. Banshihari. |
|
Nihar Ghosh |
23/07/2024 |
₹434,984.00 |
29/10/2024 |
1249/ZP |
Not started |
90
|
BEUP 42 |
|
100 |
09-02-24-25 |
Installation of Solar High Mast Light at Gurkhari Graveyard under Bagichapur GP in P.S. Harirampur block |
|
Nihar Ghosh |
23/07/2024 |
₹434,984.00 |
29/10/2024 |
1248/ZP |
Not started |
90
|
BEUP 42 |
|
101 |
09-02-24-25 |
Installation of Solar High Mast Light at Pathar Para more infront of MSK School under Gokarna GP in P.S. Harirampur block |
|
Nihar Ghosh |
23/07/2024 |
₹434,984.00 |
29/10/2024 |
1247/ZP |
Not started |
90
|
BEUP 42 |
|
102 |
09-01-24-25 |
Installation of Solar High Mast Light at Jhinakuri more under Bairhatta GP in P.S. Harirampur block |
|
Nihar Ghosh |
23/07/2024 |
₹434,984.00 |
29/10/2024 |
1246/ZP |
Not started |
90
|
BEUP 42 |
|
103 |
08-05-24-25 |
Installation of Purify Water Machine at Fulbari High School 2 pc. And Dautpur FP school (Ajmatpur GP)-58212159 |
|
PABAN BASAK |
23/07/2024 |
₹297,058.00 |
04/09/2024 |
1049/ZP |
Not started |
30
|
15th FC TIED (2022-23) |
|
104 |
08-04-24-25 |
Supply & Installation of Water Purifier cum Chiller Machine in Sayraour Kali Mandir, Thangapra Natta Mandir- 2 no, Bikoir Jr. High School -2 no & Vivekananda girls High School-2 no, Naroi Moulana Azad Academy-2 no,sankar Boys & Girls Mission(Gofanagar GP)-2 no,Baniyal High School(Gofanagar Gp)-69611202 |
|
PABAN BASAK |
23/07/2024 |
₹1,336,708.00 |
04/09/2024 |
1048/ZP |
Not started |
30
|
15th FC TIED (2023-24) |
|
105 |
08-03-24-25 |
Repairing & renovation works at Block - A, Block-B and Block-C of Dakshin Dinajpur Zilla Parishad |
|
PABAN BASAK |
23/07/2024 |
₹697,289.00 |
04/09/2024 |
1047/ZP |
Not started |
60
|
15th FC |
|
106 |
08-01-24-25 |
Construction of Rose Garder at Dakshin Dinajpur Zilla Parishad. |
|
PABAN BASAK |
23/07/2024 |
₹3,978,156.00 |
04/09/2024 |
1046/ZP |
Not started |
60
|
Horticulture |
|
107 |
06-02-24-25 |
Construction of CC road from Masjid to Afsar Miah House under Uday GP in Gangarampur P.S. |
|
PABAN BASAK |
04/07/2024 |
₹495,096.00 |
04/09/2024 |
1045/ZP |
Not started |
60
|
15th FC (22-23) |
|
108 |
06-01-24-25 |
Repair and Renovation of 2nd gate and construction of Internal road within Buniadpur College Campus. |
|
Suhita Paul |
04/07/2024 |
₹1,210,047.00 |
04/09/2024 |
1044/ZP |
Not started |
90
|
DAP (Critical Gap) |
|
109 |
05-04-2024 |
Supply and installation of Solar based LDTW ( 150 mm x 100 mm ) for minor irrigation at the land of 1) Sabnam Mustari, C/o Mojahar Alam, Birpur Kushmandi 2) Nitai Sarkar, C/o Prabash Ch. Sarkar, Saidpur, Boalder, G.P. Balurghat, 3) Wares Ali, C/o Ajijuddin Ahamed, vill – Jaharpur Elahabad GP Banshihar, |
|
Nihar Ghosh |
27/06/2024 |
₹2,390,634.00 |
04/09/2024 |
1043/ZP |
Not started |
60
|
5th SFC (23-24) |
|
110 |
05-03-24-25 |
Construction of boundary wall at ZP Land adjacent to Police Station Tapan under Chandipur GP in PS – Tapan |
|
Kalyan Bose |
27/06/2024 |
₹1,492,791.00 |
04/09/2024 |
1042/ZP |
Not started |
90
|
5th SFC (23-24) |
|
111 |
05-02-24-25 |
Construction of RCC Box Bridge (1 No x 3.0 M x 3.0 M) at Kamalpur more under Tapan P.S., Dist Dakshin Dinajpur |
|
Kalyan Bose |
27/06/2024 |
₹1,516,071.00 |
04/09/2024 |
1041/ZP |
Not started |
90
|
5th SFC (23-24) |
|
112 |
05-01-24-25 |
Maintenance of Khatkhatia Bridge on the road from Mahipal to Beltala more near Beltala more over Mankhari in PS Kushmandi |
|
Suhita Paul |
27/06/2024 |
₹1,448,099.00 |
04/09/2024 |
1040/ZP |
Not started |
90
|
DAP |
|
113 |
03-01-24-25 |
Construction of CC Road from Chheoda to Bishkuri in P.S. Kushmandi GP- Kushmandi |
|
Kalyan Bose |
18/06/2024 |
₹7,713,266.00 |
29/10/2024 |
1245/ZP |
Not started |
120
|
PATHASHREE-3 |
|
114 |
68-04-23-24 |
Supply and Installation of Water ATM infront side of Tulot High School, Vill-Tulot under Jakirpur GP in P.S. Kumarganj(Civil+ Electrical Work) |
|
PABAN BASAK |
15/03/2024 |
₹534,134.00 |
24/07/2024 |
844/ZP |
Not started |
90
|
5th SFC Tied |
|
115 |
68-03-23-24 |
Installation of Solar Street Light front side of Saddik Mondal house, Kadamathail front side of Deloyar Hossen Mondal house, Badkharna-front side of Jalal Mondal House and Masjit PS- Balurghat. GP- Nazirpur-69386295 |
|
SMRITI CHANDRA KARMAKAR |
15/03/2024 |
₹460,420.00 |
24/07/2024 |
843/ZP |
Not started |
60
|
15th FC TIED (2nd) (2023-24) |
|
116 |
68-02-23-24 |
Construction of Box Bridge (3nos x 3.0m x 3.0m) at Patul on Road from Chenchra More to Bajitpur under nandanpur GP in P.S. Gangarampur. |
|
PABAN BASAK |
15/03/2024 |
₹4,459,158.00 |
24/07/2024 |
842/ZP |
Not started |
|
5th SFC Tied |
|
117 |
68-01-23-24 |
Construction of RCC Box Bridge (2nos x 3.0m x 3.0m) at Dolkura, Mahendra under Harirampur PS. |
|
Kalyan Bose |
15/03/2024 |
₹2,930,016.00 |
24/07/2024 |
841/ZP |
Not started |
180
|
5th SFC Tied |
|
118 |
67-08-23-24 |
Installation of Solar Powered LDTW (150mm x 100mm) for Minor Irrigation at the Land of Nijrin Pavin w/o Aktarul Haque Mondal in GP-Ashokegram, Gangarampur, Dakshin DInajpur-40090 |
|
PABAN BASAK |
11/03/2024 |
₹871,692.00 |
24/07/2024 |
840/ZP |
Not started |
|
5th SFC Tied |
|
119 |
67-07-23-24 |
Construction of CC road from Ajil Molla House towards Balihar Eidgaha Pucca Road, Ramchandrapur in P.S. Tapan-68347760 |
|
Kalyan Bose |
11/03/2024 |
₹971,151.00 |
24/07/2024 |
839/ZP |
Not started |
60
|
15th FC UN-TIED (23-24) (2nd t Phase) |
|
120 |
67-06-23-24 |
Installation of Solar Street Light at Doulatpur Football Mat. GP- Mahabari in P.S. Banshihari.-70385254 |
|
Nihar Ghosh |
11/03/2024 |
₹460,420.00 |
24/07/2024 |
838/ZP |
Not started |
60
|
15th FC TIED(2nd ) (2023-24) |
|
121 |
67-05-23-24 |
Installation of Solar Powered LDTW for Minor Irrigation at the Land of Pratap Chandra Kundu in GP Uday , Gangarampur-71014372 |
|
PABAN BASAK |
11/03/2024 |
₹871,692.00 |
24/07/2024 |
837/ZP |
Not started |
60
|
15th FC TIED(2nd ) (2023-24) |
|
122 |
67-04-23-24 |
Fencing work at front side of Kushmandi Ustab Bhabhan and Construction of drain in P.S. Kushmandi. |
|
Suhita Paul |
11/03/2024 |
₹999,934.00 |
24/07/2024 |
836/ZP |
Not started |
|
15th FC Un-tied |
|
123 |
67-02-23-24 |
Construction of CC Road from Samsuddin House to Lohar Bridge(east Harsura), Harsura GP in P.S. Tapan |
|
Kalyan Bose |
11/03/2024 |
₹2,519,973.00 |
25/10/2024 |
1221/ZP |
Not started |
90
|
Repair and Maintenance |
|
124 |
67-01-23-24 |
Construction of CC Road from Zilla Parishad Road towards Hafijul Miah House in Vill-Gokulpur under Ashokgram GP In P.S. Gangarampur. |
|
PABAN BASAK |
11/03/2024 |
₹1,262,499.00 |
24/07/2024 |
835/ZP |
Not started |
90
|
5th SFC Un-tied |
|
125 |
64-11-23-24 |
Installation of Solar Powered LDTW for Irrigation at the Land of Mahammad Sahir in GP-Pundari in P.S. Harirampur-70998482 |
|
Nihar Ghosh |
22/02/2024 |
₹871,692.00 |
23/07/2024 |
834/ZP |
Not started |
60
|
15th FC TIED (2023-24) |
|
126 |
64-09-23-24 |
Construction of CC Road from Main road to Doulatpur Hatidoba, Ganguria GP Sayastabad Altab Miah House in P.S. Banshihari.68132725 |
|
Kalyan Bose |
22/02/2024 |
₹685,554.00 |
23/07/2024 |
833/ZP |
Not started |
60
|
15th FC UN-TIED (2023-24) (1st phase) |
|
127 |
64-08-23-24 |
Construction of Mukta Mancha at Najrul Smrity High School, Bagichapur under Harirampur PS-6989560 |
|
Kalyan Bose |
22/02/2024 |
₹494,911.00 |
23/07/2024 |
832/ZP |
Not started |
90
|
15th FC UN-TIED (2023-24) (2nd phase) |
|
128 |
64-07-23-24 |
Installation of Solar Powered water ATM infront of Bolla Hospital Para at front side of Kachimuddin Molla House, Vill-Bolla under Balurghat PS-69801832 |
|
Nihar Ghosh |
22/02/2024 |
₹527,774.00 |
23/07/2024 |
831/ZP |
Not started |
60
|
15th FC TIED (2023-24) (2nd phase) |
|
129 |
64-06-23-24 |
Construction of Sasan Ghat and Waiting Shed at Belkhariya Pukur west side in Vill-Chalunda under Uday GP in P.S. Gangarampur-68372152 |
|
PABAN BASAK |
22/02/2024 |
₹1,089,216.00 |
23/07/2024 |
830/ZP |
Not started |
90
|
15th FC UN-TIED (23-24) (1st Phase) |
|
130 |
64-04-23-24 |
Construction of CC Road from Baropara towards Baskuriya Pukur rest part, Mostafapur under Uday GP in P.S. gangarampur-70882132 |
|
PABAN BASAK |
02/02/2024 |
₹582,690.00 |
23/07/2024 |
829/ZP |
Not started |
60
|
15th FC UN-TIED(1st) (2023-24) |
|
131 |
64-03-23-24 |
Installation of Solar Powered LDTW for Irrigation at the Land of Sahajan Sarkar in GP-Ramkrishnapur, P.S. Kumarganj-71020232 |
|
PABAN BASAK |
22/02/2024 |
₹781,421.00 |
23/07/2024 |
828/ZP |
Not started |
60
|
15th FC TIED (2023-24) |
|
132 |
64-02-23-24 |
Installation of Solar Powered LDTW for Irrigation at the Land of Rased Mondal Sarkar in GP-Samjia, P.S. Kumarganj-71019489 |
|
Nihar Ghosh |
22/02/2024 |
₹781,421.00 |
23/07/2024 |
827/ZP |
Not started |
60
|
15th FC TIED (2023-24) |
|
133 |
64-01-23-24 |
Installation of Solar Powered LDTW for Irrigation at the Land of Ahed Ali Sarkar in GP-Bhour, P.S. Kumarganj-71018802 |
|
Nihar Ghosh |
22/02/2024 |
₹781,421.00 |
23/07/2024 |
826/ZP |
Not started |
60
|
15th FC TIED (2023-24) |
|
134 |
63-04-23-24 |
Supply of water ATM machine at Patiram High School , Patiram Vivekananda High School, Jahangirpur High School,Ashoke Gram High School , Bolla High School,kuchkari High School(Mahabari GP),Badalpur High School (Brajavallavpur GP), Gyanankur Vidyaniketan Elandari under Safanagar G.P.-67469264 |
|
PABAN BASAK |
07/02/2024 |
₹891,159.00 |
15/03/2024 |
442/ZP |
Not started |
30
|
15th FC TIED (2021-22) |
|
135 |
63-03-23-24 |
supply & Installation of Water Purifier cum Chiller Machine in Sayrapur High School-2 nBajitpur High School-2 no, Radhanagar Natta Mandir,Al-Ekra -Mission( Mahabari GP),Balapur High School(Gofanagar GP), Dangar hat High School under Kumarganj Block-2 no.-69609688 |
|
PABAN BASAK |
07/02/2024 |
₹1,019,698.00 |
15/03/2024 |
441/ZP |
Not started |
30
|
15th FC TIED (2023-24) |
|
136 |
63-01-23-24 |
Supply & Installation of Water Purifier cum Chiller Machine in Badamail L.P. High School-2 no ,Palsa TAHID mission-2 no ,Baul Hindu Milon-2, Mandir Malancha madrasha-1, Tulot High School under Kumarganj Block. -2 no,Shihol High School(Elahabad GP),Maja-Eri-academy& Darul Koran Tikarpukur (Jagangir GP), MAhabari GP office (Banshihari Block)-69622965 |
|
Kalyan Bose |
07/02/2024 |
₹1,336,708.00 |
15/03/2024 |
440/ZP |
Not started |
30
|
15th FC TIED (2023-24) |
|
137 |
62-01-23-24 |
Construction of CC Road from Chainage 985.00 mtr. of Ghoshpara-Dakshin Debipur Road to Dakshin Debipur Primary School in P.S. Gangarampur. |
|
PABAN BASAK |
02/02/2024 |
₹4,227,015.00 |
12/03/2024 |
410/ZP |
Not started |
120
|
PATHASHREE-3 |
|
138 |
61-16-23-24 |
Construction of Cc Road from Kakoti Pacca Road to Chakmahon Rejaul’s House under Jakirpur GP in P.S. Kumarganj. |
|
PABAN BASAK |
02/02/2024 |
₹2,913,462.00 |
15/03/2024 |
338/ZP |
Not started |
90
|
Repair maintenance 23 |
|
139 |
61-15-23-24 |
Construction of CC Road from Swapan Mahato House to Gajen Mahato House under Binshira GP In P.S. Hili. |
|
PABAN BASAK |
02/02/2024 |
₹1,782,353.00 |
15/03/2024 |
337/ZP |
Not started |
90
|
5th SFC |
|
140 |
61-14-23-24 |
Construction of CC Road from Pacca Road near the shop of Nirmal Sarkar at Dakshin Ramkrishnapur towards the house of Provu Minji under Deor GP in P.S. Kumarganj. |
|
PABAN BASAK |
02/02/2024 |
₹1,942,308.00 |
15/03/2024 |
336/ZP |
Not started |
90
|
5th SFC |
|
141 |
61-13-23-24 |
Construction of CC Road from Raghunathpur towards Batun Hospital main road at Batun GP In P.S. Kumarganj |
|
PABAN BASAK |
02/02/2024 |
₹990,196.00 |
15/03/2024 |
335/ZP |
Not started |
90
|
5th SFC |
|
142 |
61-12-23-24 |
Construction of CC Road from Sukur Ali House towards Subhash Roy House via Tarani Roy House under Samjia GP In P.S. Kumarganj. |
|
PABAN BASAK |
02/02/2024 |
₹1,188,235.00 |
15/03/2024 |
334/ZP |
Not started |
90
|
5th SFC |
|
143 |
61-11-23-24 |
Construction of CC Road from Deb Das House towards Saraswati Mahanta House under Panjul GP in P.S. Hili. |
|
PABAN BASAK |
02/02/2024 |
₹1,456,731.00 |
15/03/2024 |
333/ZP |
Not started |
|
5th SFC |
|
144 |
61-09-23-24 |
Construction of CC Road from Dipen Barman Land to Nitai Mondal land in P.S. Balurghat |
|
SMRITI CHANDRA KARMAKAR |
02/02/2024 |
₹1,782,353.00 |
15/03/2024 |
332/ZP |
Not started |
90
|
5th SFC 2nd Inst |
|
145 |
61-08-23-24 |
Construction of CC Road from Uttam Tailars towards Puiyakuri in P.S. Balurghat |
|
SMRITI CHANDRA KARMAKAR |
02/02/2024 |
₹990,196.00 |
15/03/2024 |
331/ZP |
Not started |
90
|
5th SFC |
|
146 |
60-07-23-24 |
Balance Portion Repairing works of toilets and kitchen shed of Harirampur ZP Ustav Bhaban in P.S. Harirampur(Civil Portion) |
|
Kalyan Bose |
15/03/2024 |
₹491,070.00 |
15/03/2024 |
330/ZP |
Not started |
90
|
5th SFC |
|
147 |
61-06-23-24 |
Construction of covered Drain from Petnidighi towards Hatkhola, GP-Maligaon in P.S. Kushmandi. |
|
Suhita Paul |
02/02/2024 |
₹1,386,056.00 |
15/03/2024 |
329/ZP |
Not started |
90
|
5th SFC 2nd Inst |
|
148 |
61-05-23-24 |
Construction of CC Road Toltala to the end of Jhap Para towards Panchidipti More at Gobra Bill in P.S. Kushmandi |
|
Kalyan Bose |
02/02/2024 |
₹1,980,184.00 |
15/03/2024 |
328/ZP |
Not started |
90
|
5th SFC |
|
149 |
61-04-23-24 |
Construction of CC Road from Afsar Miah House towards Kalam Miah House via Sadekul Miah House, Dotaripara, Bagichapur in P.S. Harirampur. |
|
Kalyan Bose |
02/02/2024 |
₹971,154.00 |
15/03/2024 |
327/ZP |
Not started |
90
|
5th SFC |
|
150 |
61-03-23-24 |
Installation of Solar Powered water ATM infront of Barampur FP School, Hazaratpur under Tapan PS-69617940 |
|
Kalyan Bose |
02/02/2024 |
₹533,582.00 |
15/03/2024 |
326/ZP |
Not started |
90
|
15th FC TIED (2023-24) (2nd phase) |
|